We are wrapping up week one of construction and are moving along nicely. We have completed the pulverizing of holes 5,7,8,9,10,12 & 13. Holes 8 & 9 are now ready for sod and the crews are coming on Monday to install our new fairways. We have completed installation of the new irrigation heads on 8 & 9 as well. #7 Fairway is rough graded and should be ready for sod by the end of the day on Monday, and #10 will be right behind by Wednesday. Our progress is right on schedule!
We also sodded the northern half of the range tee this week, and have opened the half we sodded a few weeks ago.
 |
#7 Fairway after being pulverized |
 |
#8 Fairway is ready for sod now |
 |
JR wanted to keep a close eye on our operation! |
 |
Final grading of #9 fairway |
 |
Rough grading #7 fairway |